New build progressing rapidly

P1040264 (Custom) P1040263 (Custom)

 

The new Learning Support/Sixth Form Centre with a myriad of scaffold as the roof is completed and the brickwork and internal fixings are well under way. The glass is now in the link corridor and work on the terracing is well underway.

Steel work arrives for the new sixth form/SEN extension

 

This photograph was taken on February 3rd and shows all the steel work on site which will form the new sixth form resource centre and the new SEN department. It took over 3 hours to unload the steel from a low loader and maneuvering the truck off site  proved to be a tricky challenge.

You can also see the completed steel structure for the new glazed corridor.

P1020845 (Custom)

 

Buildings Update January 22nd

Glazed corridor

The steel work nears completion for the glazed corridor at the back of the school. This should be completed by January 24th. There have been a number of unavoidable delays but things should now start to really take shape!

New drains in place

New drain in place

The new drain has now been laid along the back of the school where the new cloister corridor will be. The old drain was situated where the foundations need to go and so needed to be re-sited.